Stony Chute Rd is slated for an opening late November, with one lane access only at some sections. The landslip area that resulted in the Stony Chute Rd closure is mostly completed but in the meantime work has started on the slip between Stanger and Zouch roads.
Gallery of progress to date:
Video of Current State of Works:
Landslip and road damage remediation works as part of reconstruction funds released in response to the 2022 floods, will be ongoing in the area for the new three years, though Stony Chute Rd repairs are due to be completed by November 2026, when the road will return to two way access.
CMC Have taken up residence at their shiny new depot on Blue Knob Rd just north of Nimbin and will be tackling a range of road projects in the area in coordination with Council and State Government.
CMC Depot under construction: